Completion Date - November 15, 2022
Final Contract Value: $600,000
Owner – WSDOT
Prime Contractor – American Rock Products
Scope – Bridge approach slab replacement, expansion joint replacement, waterproof membrane & bridge deck repair.
Completion Date - November 1, 2022
Final Contract Value - $1,400,000
Owner – WSDOT
Prime Contractor – C.A. Carey Corp
Scope – ExpansionExpansion joint sealing, bridge deck rut repair, expansion joint polyester tapering.
Completion Date: October 1, 2022
Final Contract Value: $1,300,000
Owner - WSDOT
General Contractor - Combined Construction Inc
Scope - Replacement of existing modular expansion joint. Work was completed over two weekend closures.
Completion Date - October 1, 2022
Final Contract Value: $400,000
Owner – Kittitas County
Prime Contractor – Liberty Maintenance
Scope – Truss portal heat straightening & steel repair, concrete spall & crack repair, bridge rail repairs, expansion joint replacement.
Completion Date - September 1, 2022
Final Contract Value - $750,000
Owner – Snohomish County
General Contractor – Combined Construction, Inc
Scope – Bridge rail retrofit, bearing replacement, deck overlay, joint reBridge rail retrofit, bearing replacement, bridge beck overlay, expansion joint replacement, concrete spall repair.
Completion Date - September 15, 2022
Final Contract Value - $5,400,000
Owner – Stillaguamish Tribe
Prime Contractor – Reece Construction
Scope – Construction of 3,000 ln ft moment slab / barrier & 500 Ln ft of cantilevered pedestrian walkway structure. Work was completed in compressed 3 month road closure.
Completion Date - August 1, 2022
Final Contract Value - $800,000
Owner – SDOT
Prime Contractor – Kraemer North America
Scope – Place & finish 16,200 cu ft of modified concrete overlay.
Completion Date - July 1, 2022
Final Contract Value - $800,00.00
Owner - Pierce County
Prime Contractor - Combined Construction Inc
Scope - Bridge deck repair, expansion joint replacement & Polyester concrete overlay to 3 bridges at various county sites.
Completion Date - June 18, 2022
Final Contract Value - $900,000
Owner - City of Auburn
Prime Contractor - Combined Construction Inc
Scope - Expansion joint replacement, bridge deck scarification & modified concrete overlay to 1 bridge. MMA deck sealer & new joint seals in 3 bridges. Project also included channelization, signage & asphalt paving.
Completion Date - June 1, 2022
Final Contract Value - $750,000
Owner - Seattle Department of Transportation
Prime Contractor - Combined Construction Inc
Scope - Bridge seismic retrofit including abutment transverse & longitudinal restrainer blocks, Cap beam bolstering, Column bolstering, Deck retrofit using grouted longitudinal rebar, bridge deck overlay.
Completion Date - May 31, 2022
Final Contract Value - $4.750,000
Owner - City of Tacoma
Prime Contractor - Combined Construction Inc
Scope - S. Tacoma Pump Station - CFRP strengthening of clear well. Hood St Chlorination Building – CFRP strengthening, footing extensions, shear walls, structural steel, electrical/HVAC modifications. Hood St Pump Station – CFRP strengthening, structural steel, roof replacement, clear well concrete repair & lining. Hood St Reservoir – 48” pipe seismic joints, reservoir roof joint strengthening, reservoir roof coating, interior concrete repair & lining, S.S. stair tower/vents/ hatches.
Completion Date - April 1, 2022
Final Contract Value - $350,000
Owner - Seattle DOT
General Contractor - Combined Construction Inc
Scope - Construct link slabs joint retrofits, reinforce abutment with anchored bolster, bridge spall & crack repair.
Completion Date - September 1, 2021
Final Contract Value - $200,000
Owner - City of Redmond
General Contractor - Combined Construction Inc
Scope - Bridge Polymer Overlay
Completion Date - September 1, 2021
Final Contract Value - $2,000,000
Owner - Port of Tacoma
General Contractor - Combined Construction Inc
Scope - Bridge Replacement
Completion Date - June 1, 2021
Final Contract Value - $800,000
Owner - Bureau of Land Management
Prime Contractor - Rickabaugh Construction
Scope - Bridge Rehabilitation
Completion Date - May 1, 2021
Final Contract Value - $300,000
Owner - Wa Parks
General Contractor - Combined Construction Inc
Scope - Pedestrian bridge replacement
Completion Date - May 1, 2021
Final Contract Value - $700,000
Owner - WSDOT
General Contractor - Rognlins, Inc
Scope - scarification & MCC overlay, expansion joint replacement & place / finish 4000D.
Completion Date - April 1, 2021
Final Contract Value - $550,000
Owner - Alderwood Water Dist
General Contractor - Combined Construction Inc
Scope - Concrete vault & reservoir rehabilitation
Completion Date - March 1, 2021
Final Contract Value - $1,000,000
Owner - Dept of Navy
General Contractor - NOVA Group
Scope - Concrete repair to pile caps, beams, deck soffit & columns. Installation of Scope - Pier concrete spall & crack repair & placement of structural concrete.
Completion Date - January 1, 2021
Final Contract Value - $1,000,000
Owner - WSDOT
Scope - Structural steel repair & replacement
Completion Date - November 1, 2020
Final Contract Value - $500,000
Owner - City of Everett
General Contractor - Combined Construction Inc
Scope - catcher blocks, transverse stop blocks, expansion joint replacement, graffiti removal, installation of anti-graffiti coating, slope armoring, bridge drain retrofit
Completion Date - June 2020
Final Contract Value - $370,000.00
Owner - Skagit County
General Contractor - Combined Construction
Scope - Replacement of counterweight cables, sheaves & mechanics. Misc steel repair to counterweight towers & transfer span, replacement of transfer span and apron hinge pins.
Completion Date – April 2020
Final Contract Value – 2M
Owner - City of Seattle
General Contractor - Combined Construction, Inc
Scope - Seismic Retrofit to parking garage, including CFRP strengthening to columns, steel retrofit to columns & girders, concrete shear wall installation. Maintenance preservation includes concrete spall & crack repair, expansion joint repairs, misc waterproofing
Completion Date – April 2020
Final Contract Value – 2.7M
Owner - City of Seattle (SDOT)
General Contractor - Combined Construction, Inc
Scope - Retrofit Measures Include CFRP strengthening to columns, struts & arch rib. Crossbeam strengthening, infill walls, column retrofits, transverse restrainers & expansion joint replacement.
Completion Date - September 2019
Final Contract Value - 3M
Scope - CCI was a subcontractor to Advanced American Construction on this 23M contract. The overall scope of the contract was to upgrade the existing wharf. Our portion was to remove deteriorated concrete on existing wharf piers, replace corroded steel, pour new beams using high strength grout, CFRP strengthening to piers upon completion of concrete repair.
Completion Date - October 2019
Final Contract Value - $2,000,000
Scope - CCI was a subcontractor to Liberty Maintenance on this 35M contract. Our scope included rivet replacement, structural steel repair, gusset plate repair, replacement of safety cable system, installation of maintenance platforms at piers, full bridge deck rehabilitation confined to 4 weekend closures, expansion joint replacement.
Completion Date - September 2019
Final Contract Value - $420,000
Owner - WSDOT
General Contractor - Granite Construction
Scope - Expansion Joint Replacement
Completion Date - Sept 2019
Final Contract Value - $500,000
Scope - Concrete crack and spall repair to girders, piers & superstructure, bridge deck rehabilitation, expansion joint rehabilitation, bridge rail replacement & pigmented sealer
Completion Date - Aug 2019
Final Contract Value - 1M
Scope - CCI was a subcontractor to Gary Merlino Construction on this 30M concrete pavement rehab project. Our scope included bridge deck rehabilitation & expansion joint replacement to the NB I-5 Duwamish River Bridge & NB I-5 Interurban Ave Bridge. Bridge work was confined to weekend closures.
Completion Date - July 2019
Final Contract Value - 700K
Scope - Concrete surface prep & installation of epoxy coatings to all bridge columns. Concrete surface prep & installation of penetrating sealer to superstructure components.
Completion Date - Nov 2018
Final Contract Value - 1.8M
Scope - Concrete column jacketing to 6 bridges along SR 153.
Completion Date - June 2018
Final Contract Value - 650K
Scope - Seismic retrofit measures include column jacketing, longitudinal restrainers, transverse restrainers, infill walls, diaphragm retrofits, access hatch installation & CFRP strengthening.
Completion Date - April 1, 2018
Final Contract Value - $200,000
Owner - City of Port Angeles
General Contractor - Combined Construction, Inc
Scope - concrete spall repair to pile caps, bridge overlay replacement, expansion joint replacement, ADA upgrades.
Completion Date - Feb 2018
Final Contract Value - $250,000
Scope - Bridge repair including approach slab replacement & expansion joint replacement. All work confined to weekend closures
Completion Date - Nov 2017
Final Contract Value - $200,000
Scope - Expansion joint replacement & bridge repair
Completion Date - Sept 2017
Final Contract Value - 350K
Scope - Bridge deck membrane & expansion joint replacement
Completion Date - Sept 2017
Final Contract Value - $300,000
Scope - Bridge deck rehabilitation & expansion joint replacement
Completion Date - Sept 2017
Final Contract Value - $270,000
Scope - Concrete crack & spall repair to historic structure.
Completion Date - Aug 2017
Final Contract Value - 700K
Scope - Bridge expansion joint replacement to 12 bridges in Yakima Vicinity.
Completion Date - Jan 1, 2017
Final Contract Value - $700,000
Owner - Kitsap Credit Union
General Contractor - Porter Construction
Scope - Concrete spall & crack repair, Seat extensions, FRP column jackets, deck slab strengthening using FRP, cementitious & elastomeric wall coatings, chemical grouting, deck coatings, joint sealing
Completion Date - Oct 2016
Final Contract Value - $350,000
Scope - Bridge repair including replacement of drop in span, replacement of HMA & waterproof membrane, bridge rail retrofit, concrete spall; & crack repair, bridge scour repair
Completion Date - Sept 2016
Final Contract Value - $300,000
Scope - Bridge deck rehabilitation & expansion joint replacement
Completion Date - July 2016
Final Contract Value - 800K
Scope - CCI was a subcontractor to RCNW on this award winning retrofit project. Our scope included concrete spall & crack repair, longitudinal restrainers, transverse restrainers, diaphragm extensions, strut jackets & clean & seal of structure.
Completion Date - Sept 2015
Final Contract Value - $210,000.00
Owner - WSDOT
General Contractor - Tucci & Sons
Scope - Expansion Joint Replacement